CULVERCROFT DIARY

Building Culvercroft II (click on pickies below for more info)

September 2024 – Upstairs floor, wrong X, front doors.

September 2024 – Upstairs floor, wrong X, front doors.

Sept 1

Sept 30

16 September 2023

End September 2024

Back to the detail:

23rd: It’s floor pour day!

Tracy’s birthday prezzie arrives. Thank you Sobie for planning and coordinating. Thank you to DCW Polymers for a fantastic, quality, product – 100% recycled plastic. No more rotting wood / wood maintenance etc.

The new water supply fiasco. We thought South West Water were being overly cautious when they got a permit to close our lane for 5 days to connect our new water supply (to the existing meter and replacing the supply for the old bungalow). Surely just 1 days work? Well it probably would have been if the Engineers had been given a plan with the X in the right place…

The Engineer was told to install where the BIG black X is. So he dug outside our house – in the correct location – but that’s not where the BIG X is – we are the last little ‘x’ on the right hand end of the blue line. According to the BIG X, the blue line does not reach there – so they left saying they could not connect us to the mains! That’s why they needed to close the road for 5 days – to work out that the BIG X is in the wrong place and they can connect us to the mains!!!!

Now we have what we paid for – a 32mm connection to the mains…

MVHR:

Front doors in thanks to assistance from Handy Hardy again.

Next Post

October 2024 - downstairs floor and starting studwork upstairs

Tue Oct 1 , 2024
First we had to get the dpm in and seal around openings with bitumen as well as dpm. Then the vacuum pipework before the insulation… Then the insulation – and foil tape all the joints… Then the edge foam, insulation and protective membrane before the underfloor heating pipework: Then the reinforcement mesh And finally, the […]