May update – finishing the Nudura walls and, hopefully, starting on the roof…

May update – finishing the Nudura walls and, hopefully, starting on the roof…

May 1 looked like this:

And May 31 looks like this…

Eventually, after even more rain, alterations to the roof joists, a change in roofing contractor, trying to get edf to be competent and finally sorting out our water supply, we managed to get some of the joists up ‘properly’. Unfortunately it’s been too wet to leave any of the wbp hardwood ply on top so we have decided to waterproof it first so it can withstand whatever the summer (starts tomorrow) throws at us before the roofers finish the job in July. Hopefully!

So June will be all about getting the roof platform and parapets ready.

More May pickies for your delectation…

This time last year….

Next Post

June 2024: roof construction, electricity supply and the tool of the year.

Sat Jun 1 , 2024
1st June: June 7 update: Still getting the joists laid out correctly! Hopefully getting ready to do the gutter next week! June 8 update: We have fnally got all the joists in. Now we start on the levelling, getting the ply on top and aligning the joists so they are square to the ply… June […]