Driveway leveled and in. Stables relocated. Driveway and car park covered with crushed stone from old outbuildings.
Main excavation now started – excavated soil/stone/clay going into mounds that will become the ‘devon banks’ that will form the hedgerow linking east and west boundaries.
Update: Found out on the 28th July that the new planning application required for the revised location were still being validated. (It should have been done in early June!). Now we have to wait until the end of September before we can begin the works proper.